Checklist 6: Procurement and preparation of enumeration materials

ActivityDescriptionOutputResponsible Party(ies)Duration (Months)Years to Census Night
1Use of technologyConsult and make decisions on specifications for all technological requirementsSpecifications for all technological requirementsIT12
2Contracting outSelection and contracting out of census main office, logistic and processing centresRequired office structures are availableProcurement62
2Contracting outProcurement of census furniture and other materialsAll required office furniture and other equipment is availableProcurement122
2Contracting outPartnership contract to borrow equipment (if necessary)Contracts agreed and signedProcurement101
3Local and international procurementInternational logistics and customs clearanceAll procedures and requirements have been identifiedProcurement122
3Local and international procurementMake advertisements of census procurements/tender notices in mediaAwareness of requirementsProcurement00.6
3Local and international procurementMake specifications for tablets and other field devices and fill in procurement formsProcurement forms completedProcurement00.6
3Local and international procurementProcurement of field enumeration materials (printing of enumeration documents etc)Printed materials availableProcurement20.6
4Logistics for census materialsPacking of census enumeration materials into containers using the EA master list (excluding tablets)A clear material tracking systemLogistics20.6
4Logistics for census materialsProvisioning and packing of tabletsAll tablets installed with appsLogistics20.6
4Logistics for census materialsDistribution of census enumeration materials in the fieldAll centres receive materials on timeLogistics20.4